  • ENI to not deliver February’s cargo purchased at cost of 12.14%.
  • This will result in reduced supplies to power sector.
  • End consumers to get costly electricity. 

ISLAMABAD: Pakistan is expected to witness an aggravating gas crisis in February as an Italy-based LNG trading company, ENI, intimated that it will not be able to deliver its term LNG cargo due on February 6-7 by claiming the force majeure, The News reported Monday citing a senior official of the Energy Ministry.

“The gas deficit will soar as imported LNG will reduce to 700mmcfd as only five cargoes, at the price of 13.37% of Brent, and 2 cargoes, at 10.2% of Brent under GtG agreements with Qatar, would be available in February. There will be no LNG cargo from ENI at the cost of 12.14% in the month of February. And this will increase the gas crisis in the country.”

The news has disturbed the top mandarins of the Petroleum Division as the country is already facing an acute gas crisis. The crisis has been affecting domestic users in some main cities, with little to no pressure.  

The government under its gas load management plan promised gas supply to domestic consumers for cooking times in winter — three hours in the morning from 6am to 9am, two hours from 12 noon to 2pm for lunch, and three hours from 6pm to 9pm for dinner. The ground realities speak otherwise.

Relevant authorities say the impact of ENI backing out will come in the shape of reduced supplies to the power sector and the projected supply of 325mmcfd to the sector next month will not be available. 

The reliance on furnace oil-based electricity will increase and end consumers will get costly electricity. The captive power plants will be supplied gas at 50% and supply to fertiliser plants, compressed natural gas (CNG) and local industry shall remain discontinued.

Earlier, the Petroleum Division had claimed that the ENI from January 2023 onward will not default but that is not the case.

When contacted, ENI spokesperson also confirmed the development, saying: “February delivery disruption is beyond the reasonable control of ENI and due to an event of Force Majeure. ENI does not benefit in any way from the situation.”

According to the senior official, ENI defaulted five times in 2022; it failed to provide LNG cargoes in the months of March, May, July, September, and November.

Business

Exchange achieves all-time high: KSE-100 index surpasses 72,500 points

Published

on

By

With the benchmark KSE-100 index hitting a record-breaking high of 72,501 points, the Karachi Stock Exchange saw yet another incredible rise.

Within Pakistan’s financial environment, investors demonstrated a strong sense of trust in the market as the bullish trend continued.

As a result of the significant inflow of investment and optimism among market players, the index had an amazing 450-point rise during the trading session.

In their analysis of the market’s remarkable performance, financial analysts pointed to a number of causes for the upward trend, such as encouraging economic data, robust company profits, and the government’s proactive measures to promote economic expansion.

The durability and upward momentum of the market have also been greatly aided by continuous infrastructural investments and efforts meant to boost investor confidence.

In the meantime, interbank rates increased by six paisas, and the US dollar’s value saw a slight rise in the currency market. As a result of the current market conditions and the dynamic nature of foreign exchange swings, the dollar was quoted at Rs 278.45 in the interbank market.

Continue Reading

Business

The investment plan for K-Electric will be audited every three months.

Published

on

By

In light of K-Electric’s inability to persuade NEPRA with its Rs. 484 billion investment plan, the regulatory body has decided to hold off on making changes to the utility’s Transmission & Distribution Investment Plan until FY 2030.

As stated in the order, the NEPRA will select the terms of reference (ToR) for the third-party audit in addition to announcing the quarterly audit. A report on the company’s investment plan’s progress will need to be submitted every quarter.

A performance report would also be required under the investment plan by K-Electric, Karachi’s only power distribution utility, according to the statement. A secure mechanism to avoid electrical mishaps was also mandated by the authority to the utility.

In the meantime, the power distribution firm stated in a statement that the investment plan will boost the utility’s infrastructure to meet present and future demands, decrease transmission and distribution losses, and increase customer base growth.

With investments totaling Rs. 544 billion, KE has been able to more than halve its T&D losses and quadruple its customer base and power consumption since privatisation, according to the statement.

A hearing in March 2023 was held to inform stakeholders about the projects that KE management had planned for FY2024–FY2030, and the statement claimed that the plan had been presented in compliance with regulatory requirements.

In terms of investment areas including expansion, energy loss reduction, network rehabilitation, maintenance, and safety, KE claimed to have clearly defined priorities and projects for this era.

The plan calls for the construction of transmission lines and grids, which will increase the dependability of KE’s network and make it possible to take on more electricity from the National Grid.

In order to manage the city’s needs through targeted investments and tech-based interventions, CEO KE Moonis Alvi said, “We are looking to invest $2 billion in Transmission and Distribution over the next 7 years.” The work of all the stakeholders who have contributed to this trip and who will help us modernise our infrastructure and get ready for the future is something I’d like to acknowledge.

The investment plan is a supplement to the business’s Power Acquisition Programme, which outlines KE’s goal of having 30% renewable energy in its generation mix by 2030. As part of its efforts to provide everyone with access to reasonably priced energy, the firm has also been granted regulatory permission for its RFPs for 640 MW of renewable projects.

Continue Reading

Business

$399 million in airline revenue is being blocked by Pakistan. IATA

Published

on

By

Pakistan and Bangladesh have been urged by the International Air Transport Association (IATA) to promptly release airline profits that are being withheld in violation of international agreements.

“Airlines are unable to repatriate over $720 million ($399 million in Pakistan and $323 million in Bangladesh) of revenues earned in these markets, resulting in a severe situation,” an IATA statement stated.

“Money-denominated expenses like lease agreements, spare parts, overflight fees, and fuel must be paid for in a timely manner by repatriating revenues to their home countries.”

Delaying repatriation raises exchange rate risks for airlines and violates bilateral agreements’ international commitments. In order for airlines to effectively continue to offer the aviation connectivity that both of these countries depend on, Pakistan and Bangladesh must immediately release the more than $720 million that they are blocking, according to Philip Goh, Regional Vice President for Asia-Pacific at IATA.

Pakistan needs to make the difficult repatriation procedure less complicated. According to the statement, this presently includes the need to present audit certifications and tax exemption certificates, both of which create needless delays.

Approximately 425,000 jobs and $2.8 billion in economic activity were supported by Pakistan’s aviation industry prior to COVID-19. Passenger numbers are predicted to increase by more than 2.5 times by 2040 after returning to pre-COVID levels in 2023, according to the statement.

Continue Reading

Trending